The City of Cape Town thanks customers for their patience as we do necessary routine maintenance on our electrical infrastructure next week in various areas of the metro. This is how we ensure reliable electricity supply and good management of our public infrastructure. We encourage residents to always double check on the City’s social media channels to see if their area will be affected by the regular electricity maintenance during the week. Where customers are affected by supply interruptions due to normal maintenance, they should receive a door-to-door notice ahead of the planned work.

PLANNED ROUTINE ELECTRICITY MAINTENANCE 2 May – 8 May 2022

DATEAREA LOCATION/STREETSTARTCOMPLETION FORECAST
3 MayPanorama Uys Krige, Tygerberg Office Park – POSTPONED 08:0014:30
4 MayWoodridgeFlamingo Road, Dune Drive, Dune Lane, Duiker Street, Bergsig Drive, Loop Street08:0018:00
4 MayParowProvident, Kompanje, Tierberg and vicinity08:0014:00
4 May Durbanville Vlei, Van Der Stel, Maree08:0018:00
4 MayGordons BayFaure Marine, Harbour Island08:3018:00
4 MayWynbergWaterloo09:0015:00
4 MayWynbergCavan09:0015:00
4 MaySalt RiverLoco17:0022:00
5 MayGordons BayBreakwater, The Boardwalk08:0018:00
5 MayGordons BayHarbour Island, Il Ponte, Antigua Island, St Martins, Faure Marine08:0018:00
5 MayPhilippiSchaap Substation, Highwater Substation and surrounds08:3016:00
7 MayParow IndustriaSondor Performance Foam (Junction Street)08:0018:00
7 MaySea PointTramway Road and surrounds22:0000:00
8 MaySea PointTramway Road and surrounds00:0006:00
8 MaySomerset WestVenning, St James, Dirkie Uys, Reitz, Bright, St James Square, Audas St06:0018:00
8 MaySomerset WestWeber, Helderzicht, Centenary06:0018:00
8 MaySomerset WestOld Paardevlei Road, Nobel Road, Cyclonite Road06:0018:00
8 MayOttery Barbestyn, Merwe, Crescent Road, John Tyers Close, Enslin, Shawcamp Road06:0016:00
8 MayClaremontCorwin, Wodin, Protea and vicinity06:0014:00
8 May GoodwoodDingle, Hamilton, Fisher08:0013:00


*Information is complete and correct at time of publication, but subject to change due to weather and other unforeseen conditions.

*It is standard practice to notify customers of planned maintenance via a pamphlet delivered door-to-door ahead of work.

Please note: The City does not carry out maintenance from Stage 3 and above of load-shedding. Routine maintenance work is cancelled in the event of higher stages of load-shedding being implemented.

Tips:

  • Where possible, please switch off appliances at the wall socket ahead of maintenance to reduce the risk of damage caused by power surges.
  • The supply could be restored at any time, therefore residents should remember to treat all electrical installations as live for the full duration of the interruption.

City’s service channels (don't log the same request multiple times on multiple channels as this contributes to delays):
Call Centre: 0860 103 089
SMS: 31220 (standard charges apply)
Online: www.capetown.gov.za/servicerequests


End

Published by:
City of Cape Town, Media Office

You have disabled JavaScript on your browser.
Please enable it in order to use City online applications.